Alland Group were once again excited to partner with Shape to deliver a5 floor fit out (12,500m) of the ASIC office/s in Sydney.

Over the 8 months Alland Group spent onsite, ASIC needed to remain fullyoperational, therefore it was essential our program remained on target ancompleted on time.

Works included
– Removal, installation and upgrade of all electrical, lighting and data servi- CBUS / DALI lighting control system to comply with current BCA NCC 2019- AMP horizontal communications system with certification for the remainder
system warranty
– Feature lighting
– Monitored (Clevertronics HIVE) Emergency Lighting System
– General Power to Workstations, Kitchen and Cleaners Outlets.

This beautiful refurbishment was ready for the ASIC team in August 2021

I would like to thank the Alland Team for their diligence and exceptional professionalism on the ASIC L5-10 Sydney Office Fitout. Tim, Michael and the entire team were extremely proactive and helpful across all aspects of the project. As you are aware the project was Lump Sum, however the team approached a variety of site conditions and treated them as if it was design and construct, providing intelligent solutions, reducing the burden on the consultants who were unable to attend to site due to COVID and allowing the project to continue without delay. Overall, it was very positive experience working with Alland group from start to finish.

Kind Regards
Chris Wegmuller
Senior Project Manager

Details

  • Client:

    Shape  

  • Project Work:

    5 Floor Office Fitout  

  • Builder:

    Shape 

  • Site Location:

    100 Market Street Sydney